Work Progressing on Riverwalk and Parking Lot

The work on Riverwalk is progressing quickly in Bridgeview Park! The entire route has been excavated and prepared with rock. Concrete edges have been poured along large sections of the path, and we will begin installing the paving stones soon.

The new parking lot at Grove and College Streets has been excavated. The utility work that required the closure of West College this past week has been completed, so the road has been re-opened!