Paving Update: Main & College Street Intersection

Over the next two days (5/4 & 5/5), the paving contractor will be repaving College Street from Grove to First. The contractor will be milling the road today and paving it tomorrow. Portions of College Street may be closed to through traffic during this time, but the Main Street Intersection will remain open.

The intersection of College and Main is tentatively scheduled to be repaved on Wednesday (5/6). This is subject to change based on progress made early this week and, of course, weather. While you can expect some delays at the intersection, one lane of travel will be open at all times, and flaggers will be doing their best to keep traffic moving.

Your patience and cooperation are greatly appreciated during paving season. By working together, we can complete our work and provide you with safer and better-looking streets.

If you have any questions, please call B-Connected at (540) 908-4212.